Castle mold

Scope

  • TOTAL SQFT: 15,180 SF

  • Insulation: Double-layer fiberglass with clear poly vapor barrier on BSW

  • Roof Poly: Clear poly installed to underside of roof purlins using double-sided tape

  • Wall Poly: Clear poly installed on inside face of wall girts using double-sided tape

  • Liner Panels:

    • Full-height 29 GA PBR wall liner panels with trim

    • 29 GA PBR ceiling liner panels with trim

  • Doors: (3) 3’-0” x 7’-0” pre-assembled walk doors with trim kits

  • Gutters & Downspouts: Included

  • IMP Conditions:

    • 4” wall IMPs at FSW and LEW of main building

    • 4” wall IMPs at LEW, FSW, and BSW of 30’ x 6’ bump-out building

  • Framed Openings: (15) field-located framed openings at IMP locations

  • From moisture control and insulation systems to precise liner panel installation and IMP coordination, we executed a complex scope efficiently while maintaining quality and consistency. Clients should consider us for our proven capability to manage specialized interior scopes, adapt to field conditions, and deliver durable, professional results.

  • Weather is a reality in steel erection, and this project is a strong example of how we manage it. Despite active snowfall during erection, our crews maintained productivity through proper planning, experienced supervision, and safe cold-weather work practices. This project demonstrates our ability to perform reliably even in challenging weather conditions.